The Greenway projects team attended a site in Poole, Dorset to repair the tiling in a staff bathroom facility which had deteriorated to a standard below acceptable health and safety requirements. Many of the tiles on the wall had already come away and, on inspection, it was discovered that further loose tiles would also need to be removed and replaced.

However, on commencement of the works, it was found that the plaster on the wall behind had delaminated significantly, requiring complete re-skimming. The team, therefore, removed the damaged plaster from the hard wall backing in the affected area as well as the adhesive to the wall adjoining the urinal. The wall was re-plastered and left to dry.

The team then returned to the site and installed the new like-for-like white tiles and blue borders, to match the existing. All the tiles were grouted and sealed. The site was cleaned down and all waste materials removed from the site, ready for the staff to use.

To comply with current social distancing and hygiene procedures, the team was required to adopt additional health and safety measures at all times while on site.

At Greenway, we pride ourselves in the professionalism and attention to detail of all our engineers irrespective of the scope of the project. If you require internal or external works at your facility, please get in touch.