No matter what size of project, detailed scheduling is critical to its success, as demonstrated by this recent job undertaken for Integral/Thomson Reuters in Exmouth.

A new altro flooring for a shower room and new shower tray with a maintenance friendly front was required to be designed and built. The works had to be carefully planned in to minimise access to the room, being used as a wet room, which meant it had to be completely dry whilst the work was carried out.

The flooring team attended for the first visit, timed at the end of the week, enabling the room to be left unused over the weekend and the floor to settle. Engineers then attended on the Monday to design and build the new front shower tray panel for easy access and future maintenance.

The works were completed over a 2-day period spanning the weekend, minimising the disruption for users, with the room now fully back in service.